Seamlessly update your WIP report thanks to our dedicated widget, and turn it into a dynamic tool that gives proactive visibility into all projects’ performance.
Go to the appropriate dashboard that contains the WIP widget
Click the Options menu
Click Edit WIP Details
If there are summary cost codes, click the arrow on the left to expand all of them or just the specific group you want.
Enter a dollar ($) amount or a percentage (%) in the Value of Work Completed column. If you input a dollar amount, the percentage will update automatically, and the same goes for entering a percentage.
The variance and accruals column will adjust automatically. Also, if you enter 100% in the field, the Value of Work Completed will update to equal the Forecast Final Cost value.
Once finished, click Save